Olkiluoto 3 stops again – production outage lasts just over eight days
Olkiluoto 3 will be disconnected from the electricity grid today, 28.11. at 16:30 to repair a valve fault in the secondary circuit. The outage will last until 7.12. at 3:00. OL3 covers approximately 14% of Finland's electricity demand; OL1 and OL2 will continue normally.
Olkiluoto 3 will be disconnected from the electricity grid today, Saturday, November 28, at 16:30. The reason is a valve fault in the secondary circuit that cannot be repaired while the plant is running. For this reason, the plant will be shut down for the duration of the repair.
The outage begins today, Saturday, November 28, at 16:30 and ends on Monday, December 7, at 3:00. The outage will last just over eight days.
Key figures
- OL3 power: 1,600 megawatts – Finland's largest single electricity production unit, approximately 14% of Finland's electricity demand.
- Outage: 28.11. at 16:30 – 7.12. at 3:00.
- During the previous outage on Thursday, November 26, the average price of spot electricity was 32.62 cents per kilowatt-hour, while on Wednesday it was 17.30 cents.
Weekly outages
The valve fault was detected on Friday, November 20, when the plant's power was increased after a maintenance outage. Power was reduced on Wednesday, November 25, to approximately 60 percent. Production was interrupted on Thursday, November 26, at 4:15, and the plant returned to production on the same day around noon, faster than expected. On Friday, November 27, power was reduced again to investigate the fault. Now, the same fault is causing a longer, over eight-day outage.
OL1 and OL2 will continue production normally.
What does this mean for you?
If you have a spot-price electricity contract, hourly electricity prices may be higher when Finland's largest single production unit is off the grid. During the previous outage on Thursday, November 26, the average price of spot electricity was 32.62 cents per kilowatt-hour, while on Wednesday it was 17.30 cents. Prices cannot be predicted in advance: they are determined by supply and demand.
Sources: TVO press release 25.11.2026 (production interruption) — https://www.tvo.fi/ajankohtaista/tiedotteetporssitiedotteet/2026/ol3ntuotantokeskeytetaanventtiilivianselvityksenvuoksi.html ; TVO press release 26.11.2026 (return to production) — https://www.tvo.fi/ajankohtaista/tiedotteetporssitiedotteet/2026/ol3palaasahkontuotantoonarvioituaaiemmin.html ; Nord Pool market messages (UMM) — https://umm.nordpoolgroup.com